Help needed: Can someone please summarise the difference between resource levelling and smoothing?

Michelle Greaves Also after being on the course....Resource smoothing is done BY the project manager (PM) to smooth out peaks in resources e.g. if you need 10... Show more 10 months ago
loader
loader
Attachment
Paul Naybour Hi For me the key difference is that with smoothing you use the float to reduce peak demand for resources, by keeping the end date the same. With... Show more 10 months ago
loader
loader
Attachment

About Parallel

We give all of our clients a personal service, blending traditional and modern learning techniques to deliver a flexible training solution. We are a small and specialist project management training provider with a global reach. Our consultants are best in class and are equally at home delivering off the shelf courses or a solution tailored to your specific needs. We have designed this website to give you a flavour of what we do. If you like what you see, please do get in touch to discuss how we can support your organisation.

Aspect