Q5. This question is in two parts answer both parts

James Wilkins Discussion started by James Wilkins 5 years ago

 


Normal 0 false false false EN-GB X-NONE X-NONE

(i)            Explain how each of the following estimating methods are used to estimate the costs or timescale of a project

a.     Comparative

b.    Parametric

c.     3 Point Estimating


Comparative – This is where a single known project is taken, scaled up and any allowances are made so that a better value of the project can be produced. This may be if an office block offers 3000 sq.ft of letting space, but the subject property in question has 4000 sq.ft, the cost can be scaled up proportionately by 4/3. Any variables would have to be taken into account such as specification of the building or services the building already has in space, which will affect the cost estimate.

 

 

Parametric – This method is where a known number for a unit is multiplied by the amount required. This may be a road whereby a single mile costs £1 million, and the project required 10 miles, therefore the cost is estimated at £10 million. This is a quick and easy method of estimating cost, but can be full of risks such as baseline data not being correct. This would then be multiplied by 10 causing significant errors later in the project life cycle.

 

 

3 Point Estimating – This method seeks to remove some of the vagaries from a single point estimate. It uses the best case, most likely and worst case for either cost or time. A PERT (Project Evaluation and Review Technique) can be used in this method, which takes into account the three varying costs/durations and produces a best estimate between the three. The last variation of this method is called  Monte Carlo modeling which is a further extension of this technique.

 

 

 

(i)            State 4 generic causes of estimating error

 

 

1.     Assumptions – These are made during a project in order to get processes moving and carry a large risk as they are essentially educated guesses and can result in changes later on, but can be analyses by the project manager to help mitigate the risks.

 

 

2.     Lack of previous data – A project which has never been undertaken before will carry a risk that little of no knowledge is available of how to do it, which means a significant amount of work will be required upfront to help the estimate, but even so the risk is still increased.

 

3.     Risks – The allowance of a risk must be taken into account for both the duration and cost of the project, as without this allowance, the project can over-run by an unknown amount unless the risks are evaluated and allowed for.

 

4.     Subjectivity – An estimators experience and therefore their output into the project such as cost, will be subjective to their previous dealings, and so the Project Manager must take this into account and try to dissect any subjective costs which may not be relevant to the project. 

Replies
Paul Naybour
Paul Naybour James, well done, almost text book answers. Ten more like this and you should pass. 5 years ago
loader
loader
attachment
You need to be a member of this group before you can participate in this discussion.

About Parallel

We give all of our clients a personal service, blending traditional and modern learning techniques to deliver a flexible training solution. We are a small and specialist project management training provider with a global reach. Our consultants are best in class and are equally at home delivering off the shelf courses or a solution tailored to your specific needs. We have designed this website to give you a flavour of what we do. If you like what you see, please do get in touch to discuss how we can support your organisation.

Aspect