Feedback required - Describe five key activities that a...

Adam Williams Discussion started by Adam Williams 2 years ago
Describe five key activities that a project office may undertake

1) Administrative support and guidance such as filing and management of documents. These include assisting with the change control procedure. Assisting with risk and issue paperwork. Supporting the project manager during absences.
2) Collection of reports and analysis of project information. Such as timesheets and any other reports that the project manager may require. Sit in on workshops to help gather information such as risk. For example, whilst the project manager is working on another project, a member of project support attends a risk workshop and is informed of a new risk. He can then pass this on to the project manager who can take the appropriate action.
3) Where the PMO has expertise in project management fields. This will ensure that project managers are mentored and coached in the various tools and techniques. For example an expert in risk management can ensure project managers are running their risk workshops in the most effective manner.
4) Continuous improvement. Ensuring that lessons are captured and made available across the organisation. For example, whilst building a new railway, a track laying team discover a more efficient way of laying their track. If this is passed on to the rest of the organisation, it may well mean the project can complete ahead of schedule.
5) Centre of Excellence. To act as a centre not only for strategic implementation of projects, but for the portfolio too. This can also be called the EPMO or Enterprise Project Management Office.
Replies
Paul Naybour
Paul Naybour Yes quite often the PMO can provide coaching and mentoring to the project managers, although this can be in conflict with any project assurance roles. 2 years ago
loader
loader
attachment
Nathalie
Nathalie Thank you Paul but what do you mean exactly by assurance roles? 2 years ago
loader
loader
attachment
Paul Naybour
Paul Naybour The PMO will often audit the project to check it is compliant with process and procedure. 2 years ago
loader
loader
attachment
You need to be a member of this group before you can participate in this discussion.

About Parallel

We give all of our clients a personal service, blending traditional and modern learning techniques to deliver a flexible training solution. We are a small and specialist project management training provider with a global reach. Our consultants are best in class and are equally at home delivering off the shelf courses or a solution tailored to your specific needs. We have designed this website to give you a flavour of what we do. If you like what you see, please do get in touch to discuss how we can support your organisation.