How to draw a gantt chart with the total flow for all...

Laila Elerkessousi Discussion started by Laila Elerkessousi 5 years ago

Hi Paul, your help would be appreciated. 

The question from the mock up exam is: Using the fully analysed netword on the 'back page', draw a Gantt chart showing the critical path and total float for all items not on the critical path.

 

Showing the critical path was wasy to do following the book explanation, but I'm not sure how to show the total float. In the book it shows the Free float by dotted line, but can't remember finding how to show Total Float on Gantt chart. Can you please tell me how that is done, or point me to somewhere I can see it.

Thank you

Laila

Replies
Paul Naybour
Paul Naybour Hi

the total float is not normally shown on a Gantt chart, if can be done in MS project by drawing a bar from early finish to late finish. Adrian (you...
Show more
5 years ago
loader
loader
attachment
Laila Elerkessousi
Laila Elerkessousi Alright, will remind him next week. Thank you for the reply 5 years ago
loader
loader
attachment
Paul Naybour
Paul Naybour I sent Adrian an e-mail last night, let see if he remembers. 5 years ago
loader
loader
attachment
You need to be a member of this group before you can participate in this discussion.

About Parallel

We give all of our clients a personal service, blending traditional and modern learning techniques to deliver a flexible training solution. We are a small and specialist project management training provider with a global reach. Our consultants are best in class and are equally at home delivering off the shelf courses or a solution tailored to your specific needs. We have designed this website to give you a flavour of what we do. If you like what you see, please do get in touch to discuss how we can support your organisation.