APMP Study Group
Category:
Created:
Tuesday, 29 November 2011
Group Admins:
-
Posted a new discussion, Possible APMP Question: Explain five distinct benefits to be gained from managing groups of projects as a programme rather than as individual, unconnected activities1) Improved ability to manage project interdependencies. Through managing the related projects a program, the programme manager has greater visibili ...
-
Posted a new discussion, Explain five elements of a stakeholder analysis processIdentify: The first step is to identify which stakeholders are relevant to your project. In a new project you might have to do this from scratch and u ...
-
Replied to the Possible APMP Question: What would be the consequences of poor requirements management?Hi A very good answer for the first four, ten more like this and you will pass Always think about the impact on 1) Time 2) Cost 3) Quality 4) Team
-
Replied to the Possible APMP Question: What would be the consequences of poor requirements management?1. If functional and non-functional requirements are not properly gathered in the concept and accurately refined in the definition phase, they would p
-
Spot-on more is better. You are also right as describe is only 2 sentences, however your answer only has one sentence. I always recommend 2-3 sentence
-
Is it always best to do more in the exam than less Paul? I was under the impression that "Describe" was one to two sentences and "Explain" was two or
-
Dave Your answer is along the right lines, but for the exam it is too brief. For each point you must include 2-3 sentences. For example you first poin
-
1.Project management is concerned with the delivery of products, whereas portfolio management is concerned with the delivery of strategic goals for th
-
How do you separate the project requirements and constraints. I find myself falling into the trap of describing a requirement as a constraint. Are they the same thing or should be described in a different context? Could you provide some examples of what is a constraint or a requirement using the Whirlwind Bikes case study? Thank you :o)
Paul Naybour A requirement has to do with the performance characteristics of the product, weight, person size and reliability. These are tested during the product acceptance. There are lots of these in Whirlwind Bikes. Whereas a constraint is imposed on the project delivery, only two people, much be completed by a certain date, 12 periods away.21 days ago -
Hi,
I've just finished reading section 8.5 - Change Control in the study guide but the Whirlwind Bikes task at the end doesn't seem to make sense and has the same wording as the 7.2 Stakeholder Management WW task. Please can you confirm what it is that we need to carry out for this task (P210).
Thanks
Paul Naybour Carl I am sorry about this printing error the questions are correct, just the header text is wrong, it should say "what would you do when faced with these changes". We are planning a up-date of the book, but we are waiting till we see the changes in the new version of the APM BoK which is due out in the summer, before we do the re-fresh. By the way the BoK re-fresh is not expected to affect the exams for 18 months or so, but it is in the hands of the apm.17 days ago -
Hello, I am new to this and have bought the book to help me prepare for the exam. Please can you point me to SADBET in the book I and trying to develop acronyms and mind maps to help me remember.
Thanks
Paul Naybour Also you might like IAPM for the core processes
Identify
Assess
Plan
Manage
You can use this as the basis of most of the processes like change control, risk management, stakeholder management,requirement management. It will need minor modification in most cases but should help you remember the overall structure.23 days ago -
sorry, typed too quickly i meant benefits of project governance not Project Management! I think the benefits of the different parts of SADBET would cover the project governance one.
Thanks though! -
Glenn,
Further to your comments about Lifecycles I would make two points.
Firstly the four phase lifecycle you refer to is known as the "Project Lifecycle" but you may also have come across the "Extended Lifecycle" or "Product Lifecycle". This has the additional two stages of "Operations" and "Termination". Depending on the context it may be appropriate to adopt the latter (e.g. if you were car -
Hi,
On a question re the benefits of effective Project Management, if I talk about SADBET and explain the benefits of having each one, am i talking about the right thing?!
Thank you! -
Re quick quiz in section 4.1 project life cycles questions 9
The statement: The PM plan is not started until the beginning of defintion is FALSE. Why is this I thought it would be true?
Paul Naybour The PM plan is started from the very start of the project. it is finished by the end of definition.27 days ago
Association of Project Management Professionals (APMP) study group.
What is the APMP?
The APMP is the foundation level qualification on Project Management from the Association for Project Management. It it the first step many project managers take in developing professional qualification to support their careers.
What are the benefits of joining this APMP Study Group?
Join this group for
1) Access to tutor support for your APMP study
2) Answers to the Parallel APMP Study Guide Quick Quiz Answers (clicking on the "Announcements" tab above once you have joined the group)
3) Get tutor feedback on your answers to APMP sample questions and get feedback from our trainers
4) Share your learning experiences with other individuals studying for the APMP
To join this group click the Join Group Icon to the right. It is FREE for anyone preparing for the APMP.
What is the APMP?
The APMP is the foundation level qualification on Project Management from the Association for Project Management. It it the first step many project managers take in developing professional qualification to support their careers.
What are the benefits of joining this APMP Study Group?
Join this group for
1) Access to tutor support for your APMP study
2) Answers to the Parallel APMP Study Guide Quick Quiz Answers (clicking on the "Announcements" tab above once you have joined the group)
3) Get tutor feedback on your answers to APMP sample questions and get feedback from our trainers
4) Share your learning experiences with other individuals studying for the APMP
To join this group click the Join Group Icon to the right. It is FREE for anyone preparing for the APMP.
Hi
The typical marking times for the APMP exam are 6-8 weeks, some times longer if members of the group are bourderline and the papers are double marked.
The typical marking times for the APMP exam are 6-8 weeks, some times longer if members of the group are bourderline and the papers are double marked.
Hi
A very good answer for the first four, ten more like this and you will pass
Always think about the impact on
1) Time
2) Cost
3) Quality
4) Team motivation
5) Safety
generally you can build a question around these five elements for most of the questions like this.
Spot-on more is better. You are also right as describe is only 2 sentences, however your answer only has one sentence. I always recommend 2-3 sentences, including if at all possible an example, for both describe and explain. Seems to work as quite often we get 100% pass rates. Ping over another question and I will take a look.
Cost effective mean that a safe working environment is less likely to result in accidents and near misses. Accidents are expensive in terms of time lost, time spent investigating the causes not to mention the cost of prosecution. It is much better to set up a safe working environment from the start.
There is a better answer to this question here http://www.parallelprojecttraining.com/community/study-groups/viewdiscussion/47-weekend-homework-for-those-preparing-the-the-apmp-exam-describe-five-health-and-safety-duties-of-a-project-manager?groupid=2
Paul,
Thanks for that.
Mike
Not bad but here are a few improvements to your answer.
1. One advantage of EVM is it allows the performance to be assesses against the baseline. This is done by converting the plan, progress and cost into a common currency. EVM gives an overall view of the project performance based on the value of useful work done at that point in time, relative to the baseline cost/programme. For example if the package is 10% complete, compared to a planed completion of 40% and spent 50% of the budget this is bad news – as we are likely to overspend.
2.One disadvantage of EVM is that the assessment of the useful work done is usually based on the percentage complete of an activity. This exercise is subjective and can lead to potential errors in the EVM analysis. For example the old adage in IT that the source code is 90% complete for 90% of the time.
3.One dis-advantage of EVM is the additional set-up work. To allow earned value analysis to be undertaken the baseline schedule needs to be constructed in an appropriate way to judgement of cost and budget against. This can often involve additional work to develop the project schedule to a point at which the information/detail is appropriate to be used by the process.
4.On major advantage of EVM is the ability to produce accurate forecasts. The Earned Value analysis generation of Schedule and Cost Performance Indices (SPI/CPI). These indices can be used to extrapolate the Estimate At Completion (EAC) and Planned Completion based on current project performance. Often these can give a good inform the assessments made by the project manager.
5.EVM can be useful when planning resources. The use of EVM outputs can allow the Project or Programme manager to identify projects or programmes that are underperforming or over-performing. As a result they can manage or re-allocate resources to help bring the project back on track. For example reassign resource on a project that is well ahead of programme to help manage project that is late and under spent.
The use of project planning software is widespread through the Project Management community. A number of the advantages and disadvantages are discussed below:
1.Flexibility. The functionality and flexibility provided by modern planning software means it is easy to use. This allows the planner/project manager to undertake ‘what-if’ or scenario based models and look at the effects on the critical path and activity float.
2.Reduced costs. The ease of use mean that less time is required to create the project plan. The software will run the forward and backward passes quickly and allow flagging of errors in the logic.
3.Ongoing update and monitoring. The approach to capture of the Gant Chart allows the project programme to be updated regularly and capture costs so that it can be used to track progress against baseline and calculate EVM.
4.Dumbing down. The ease of use and access provided to multiple users can dumb down the activity of planning. The risk is that it becomes a tick box exercise and does not generate the value for the Project Manager of physically examining the critical path and float in detail.
5.Authoritative appearance. The links of modern planning software into corporate databases and reporting can make the planning process appear authoritative and controlling. The risk is that this again drives a tick box process and is used to judge the project not manage it.
Health, Safety & Environment is a core duty of the project manager. Requirements are driven by corporate governance and legislation such as the Health & Safety at work act 1974 and CDM (Construction, Design and Management) regulations. This is governed by the HSE (Health and Safety Executive) within the UK. Five Key duties of the project manager include:
1.Ensuring there is a Health, Safety & Environmental plan in place on the project. This will often form part of the Project Management Plan. This document will describe how the process will be managed, who is involved, training requirements, tool to be used and how it incidents/accidents (RIDDORs) will be reported.
2.Ensure appropriate Risk Assessments are undertaken on the project. Undertaking risk assessments allows those at work to be aware of risks to themselves and those in proximity to their works and hence to ensure proper control or mitigation actions are in place. Risk assessments may include Display Equipment/ Workstation assessment or part of construction site Method Statements.
3.Ensuring proper and appropriate training is in place and undertaken. This allows those at work to become aware of the hazards around them and what they should/need do to protect themselves and others.
4.Ensure appropriate Protective Equipment is provided. This is to protect individuals from hazards that may be present. For example construction site works will wear a hard hat, eye protection, gloves and high visibility clothing (Hi-Vi).
5.Ensure that Health, Safety and Environment reporting is open and honest. For example reporting near ‘misses’ and incidents from the ‘grass roots’ level. This allows behaviours and improvements to be put in place within the project.
Thanks for the feedback, I am glad you like the pod casts. They are quite good at covering the topic in more detail. I know we didn't do every topic, some are a bit difficult in this format. We also have been a bit busy recently. May be I can get John and me around the microphone soon. What topic would you like the most.
