Just wondering if I have done the calculations correctly for the Earned Value Whirlwind Bikes Case Study:
CPI = 97.18%
SPI = 71.13%
SV = £ 56,000
CV = 4,000
Actual completion 16.8 Weeks
Estimate at Completion: £ 306,647.45