Feedback Please – Earned Value Whirlwind Bikes Case Study

Paul Naybour Paul Naybour

Published: 23rd January 2016

Hi

Just wondering if I have done the calculations correctly for the Earned Value Whirlwind Bikes Case Study:

CPI = 97.18%

SPI = 71.13%

SV = £ 56,000

CV = 4,000

Actual completion 16.8 Weeks

Estimate at Completion: £ 306,647.45

Thanks,
Steve

Paul