PMP Sample Questions

Home Forums PMP Study Group PMP Sample Questions

This topic contains 2 replies, has 1 voice, and was last updated by  Paul Naybour 6 years, 1 month ago.

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #15411

    Paul Naybour
    Moderator

    Regarding management and leadership all of the following are true except 

     

    On a project, particularly a larger project, the project manager is generally expected to be the project’s leader as well. 

    Technical leadership is of primary importance in project management 

    Managing is primarily concerned with consistently producing key results expected by stakeholders

    Leading involves establishing direction, aligning people, motivating and inspiring 

    Answer: B 

     

     

    A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time.Each project would take 9 months and would cost $250,000. 

     

    The first project is a process optimization which would result in a cost reduction of $120,000 per year.This benefit would be achieved immediately after the end of the project. 

    The second project would be the development of a new product which could produce the following net profits after the end of the project: 

     

    1 year: $ 15,000 

    2 year: $ 125,000 

    3 year: $ 220,000 

     

    Assumed is a discount rate of 5 % per year.Looking at the present values of these projects’ revenues in the first 3 years, what is true? 

     

     

    Both projects are equally attractive. 

    The first project is more attractive by app.7%. 

    The second project is more attractive by app.5%. 

    The first project is more attractive by app.3%. 

    Answer: D 

     

     

    A production process has been defined as part of an industrial equipment manufacturing project.The process is intended to produce steel bolts with a length of 20 cm.The acceptable control limits are 19.955 cm and 20.045 cm. 

    The measurements made at the end of the process yielded the following results: 

     

    20.033 cm, 19.982 cm, 19,995 cm, 20.006 cm, 19.970 cm, 19.968 cm, 19.963 cm, 19.958 cm, 19.962 cm, 19.979 cm, 19.959 cm. 

     

    What should be done? 

     

     

    The process is under control.It should not be adjusted. 

    The process should be adjusted. 

    The control limits should be adjusted. 

    The measuring equipment should be recalibrated. 

    Answer: B 

     

     

    What are the 4 stages of team development? 

     

    Forming, Storming, Norming, Performing. 

    Enthusiasm, Hope, Panic, Solution. 

    Assignment, Kickoff, Training, Communicating. 

    Direction, Motivation, Cooperation, Collaboration. 

    Answer: A 

     

     

    During a software project Earned Value Analysis is performed and gives the following results: 

    EV: 523,000; 

     

    PV: 623,000; 

     

    AC: 643,000. 

     

    Which results are correct? 

     

     

    CV: +120,000; SV: +100,000. 

    CV: +100,000; SV: +120,000. 

    CV: -100,000; SV: -120,000 

    CV: -120,000; SV: -100,000. 

    Answer: D 

     

     

    Which of the following is not normally an element of the Project Charter? 

     

    The formal authorization to apply organizational resources to project activities. 

    Work package descriptions. 

    The business need that the project was undertaken to address. 

    The product description or a reference to this document 

    Answer: B 

     

     

    Which process is applied to break down the project into smaller, more manageable elements? 

     

    Scope Planning. 

    Activity Duration Estimating. 

    Scope Definition. 

    Scope Verification. 

    Answer: C 

     

     

    Which of the following Tools and Techniques are part of Risk Management Planning? 

     

    Risk planning meetings. 

    Documentation reviews. 

    Data precision rankings. 

    Diagramming techniques. 

    Answer: A 

     

     

    All of the following statements concerning project stakeholders are true except 

     

    Differences between or among stakeholders should be resolved in favor of the customer. 

    Managing stakeholder expectations may be difficult because stakeholders often have very different objectives, that may come into conflict. 

    Project stakeholders may influence the course of the project and its results. 

    Differences between or among stakeholders should be resolved in the most cost efficient manner consistent with project objectives. 

    Answer: D 

     

     

    Which of the following is the output of Source Selection? 

     

    Proposals. 

    Evaluation criteria. 

    Contract negotiation. 

    Contract. 

    Answer: D

    #15412

    Paul Naybour
    Moderator

    nteresting comment
    readily admit it was one of the most difficult tests they had ever taken
    . I did my PMP exam several years ago, many of the question relate to general project management principles which require no knowledge of the PMBoK, but a good understanding of project management. To pass you do need to know you way around the PMBoK, but some people want to memorise the whole book. This is not the best approach. Much better to understand the philosophy and how to apply it. This makes the PMP much easier. It’s not as hard as say an MBA…..

Viewing 2 posts - 1 through 2 (of 2 total)

You must be logged in to reply to this topic.