Scheduling

Paul Naybour Paul Naybour

Published: 16th April 2013

Paul hi,

When drawing out the normal path in a Gantt chart do i start task C straight after the task B duration (1week) or total float (4weeks) duration?

 

  1. Student says:

    The convection is to start on the early possible dates, i.e. Early Start. Does this answer your question