Paul hi,
When drawing out the normal path in a Gantt chart do i start task C straight after the task B duration (1week) or total float (4weeks) duration?
Paul hi,
When drawing out the normal path in a Gantt chart do i start task C straight after the task B duration (1week) or total float (4weeks) duration?
The convection is to start on the early possible dates, i.e. Early Start. Does this answer your question